Rahughat hydropower project resumes construction after five years

रेडियो नेपाल २०७६ असार १३ गते १३:३६

June 28, Myagdi: Rahughat Hydropower Project in Rahughat, Myagdi district, stalled for the past five years has resumed construction.

Developed by the Nepal Electricity Authority (NEA) in 2066 BS, the project halted in 2066 BS after the contracting company went bankrupt.

Although the contractor was agreed upon to complete the project in 2070 BS, only approximately 10 percent of construction work was completed in five years. According to Ganesh KC, managing director of the Nepal Electricity A’s subsidiary Raghuganga hydropower limited, Construction of a tunnel under the project has started a week ago. The project has initiated a ‘company model’ after breaking the previous agreement.

सम्बन्धित

452 to be decorated with medals on Baisakh 1

१ घन्टा अगाडि रेडियो नेपाल

19 injured in first day of Bisket Jatra

१ घन्टा अगाडि रेडियो नेपाल

One more arrested in bomb blast incident

१ घन्टा अगाडि रेडियो नेपाल

Gold entrepreneur shot dead

१ घन्टा अगाडि रेडियो नेपाल

Mid-night fire in furniture

२ घन्टा अगाडि रेडियो नेपाल